Manufacturing Operational Upgrade, Compressor Tie-In

The Problem

The client contacted Agilitech to provide electrical construction services as they needed new electrical feeders for two of their main plant compressors. The work had to be carried out during a scheduled plant outage for maintenance, so that it would not interrupt the operation and output of the plant. This gave the team a 72 hour window to perform the installation and bring the plant back up to full operation.

Our Solution

After careful evaluation of the entire scope of the work, Agilitech developed an execution plan in close collaboration with the plant’s operation staff. We developed an accurate estimate that included materials and takeoffs, and submitted it to the client for approval. Once the execution plan and cost were approved, we scheduled the necessary resources, ordered the materials, staged for the agreed start date, and carried out the construction.

The Results

Construction was successfully completed according to the execution plan, with the correct amount of resources and within the 72 hour outage window, including commissioning support for the compressors. The compressors were restored to full operation and the project came in on time and under budget.